Project write-downs in major risk projects under control
Caverion
Building Performance
> In 2021, Caverion critically assessed its final
remaining major risk project at the end of
the year
> The write-downs from this major risk project
amounted to EUR 4.0 million in 2021
> The project is now handed over to the
customer, however final discussions
between the parties are still ongoing
Major risk projects include only one risk project in Germany in 2019-Q2/2022.
In 2018, major risk projects included three completed Large Projects from
Industrial Solutions.
Write-downs in major risk projects, EUR million
Number of major risk projects
27.1
3
9.3
17.1
12.8
1 -
1
4.0
0.0
2017
2018
2019
2020
2021
Q2/2022View entire presentation