Investor Presentaiton
Flexible and long-term investment strategy
Note: Click to view National ten year grid development plan in Finland
Forssa reserve power plant
Yllikkälä Huutokoski B 400 kV
Hyvinkää - Hikiä 400 kV
Estlink 2 DC connection to Estonia
Ulvila - Kristine stad 400 kV
Hikiä Forssa 400+110 kV
-
Hirvisuo Pyhänselkä 400 kV
Lieto - Forssa 400+110 kV
Hikiä Orimattila 400 kV
Reinforcement of Oulujoki region network
Forest Line
3rd AC interconnection to Sweden
Grid connection of nuclear and wind power
Kvarken DC
Reinforcement of Helsinki region network
Reinforcement of Lake Line
60
60
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
90% of new power lines will
be constructed along or next
to an existing right of way
EIA/Preliminary design
Detailed planning and permissions
Implementation
400 kV main grid
400 kV under construction
main grid base line scenarios
Keminmaa
Hirvisuo
Kvarken DC
Pyhäselkä
Forest Line
Lake Line
Tuovila
Kristinestad
Fingrid has a long-term planning horizon for investments
Fingrid Debt Investor Presentation
30.9.2018
Huutokoski
Petäjävesi
Ulvila
Ylikkälä
Forssa Hikiä Koria
Lieto
FINGRIDView entire presentation