3. The Power Sector in the National Budget for FY2022
3.3 ADP Allocation for BPDB
Relative Performnace of Project Completion, FY21 & FY22
.
Majority of projects are at the early
stage of implementation
18
16
14
12
•
About 38.2% of projects will be
implemented less than 50% level
The situation did not improve
from the last year (Fig above)
The status of carryover projects is
very shocking
•
15% projects would be
completed by at best 20%
13% projects would be
completed by at best 40%
Majority of projects have lost their
track of project completion cycle (Fig
below)
10
88
420
Zero
>1-10%
>10-20%
>20-30%
■Possible implementation in FY21
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
<1%
A part of the projects which are
allocated for completion by
FY2022 may not be completed on
time
Zero
>20-30%
>30-40%
>40-50%
>50-60%
>60-70%
>70-80%
>80-90%
Possible implementation rate by FY20-100% or more...
Comparison of Completion Rate of Similar Projects
between FY2021 and FY2022
>1-10% >10-20% >20-30% >30-40% >40-50% >50-60% >60-70% >70-80% >80-90% >90-100% Total
Possible completion rate in FY22
■>50-60%
■>80-90%
>1-10%
■>30-40%
■>60-70%
■>90-100% or more than 100%
>10-20%
■>40-50%
>70-80% 27View entire presentation