The What and Why: Key Drivers of Decision to Pause
Financings
Milestones (1)
Rochester Hub
Koch Investment
$100M
DOE
Application
LG Investment
$50M
Sept - Dec
2021
Rochester Hub
Project Approval
Glencore
Investment $200M
-
Jan Dec 2022
DOE Conditional Loan
Commitment for gross
proceeds of up to $375M
Gained Critical
Environmental Permit
Rochester Hub
CAPEX to date of
$178M
(1) Excludes the spend of $92.2M on process buildings and warehouse;
Escalation of Construction Costs
Recent increase in construction activity, identified
trends indicating significant increase in
construction installation costs
Reflecting these costs resulted in forecast of
project cost substantially higher than previously
disclosed budget of $560M
+
Initial Anticipated
Closing of DOE Loan
Jan - Oct 2023
Largely Completed
Engineering and
Procurement
Rochester Hub
CAPEX to date of
$227M
Financing
Project Milestones Delays
Previous Revised
Anticipated Closing
of DOE Loan
Anticipated Closing of the
Buildings Financing
Transaction
Rochester Hub
CAPEX to date of
$301M
Original Target
to Commence
Commissioning
Delayed Financings
DOE: Li-Cycle delayed from initial anticipated closing; reached final stage for
loan commitment for gross proceeds of up to $375 million
Engaging the DOE on the comprehensive project review to close the
loan agreement
Buildings leasing arrangements caused complexity in closing DOE loan;
building leasing arrangement no longer pursued
Note: DOE refers to the Department of Energy; NYSDEC refers to the New York State Department of Environmental Conservation; LPO refers to the DOE Loan Programs Office; Rochester Hub capex to date figures are as of the relevant reported quarter
and are unaudited