Progress on 37 National Strategic Project (PSN)
During 1st Quarter of 2021 (Covid-19 Pandemic Conditions), there were 8 PSN Projects that were declared Partially Operated,
and 22 PSN Projects that were successfully pushed through the Preparation Stage to the Transaction and Construction Stage.
Successfully pushed PSN Projects pass
the Preparation Stage
Successfully pushed PSN Projects
Start Operated Partially
23%
No
PSN Projects
Investment
Value
(in IDR Bio)
22
PSN
1
Jalan Tol Serpong - Cinere
2.219
Jalan Tol Cimanggis - Cibitung
4.524
77%
Penambahan Lingkup Jalan Tol Ngawi -
3
1.783
Kertosono Kediri
5 Projects exit the
Preparation Stage to the
Transaction Stage
There are 22 PSN Projects with a total
investment value of IDR 392.6 trillion which is
divided into 8 sectors:
3 Toll Roads (IDR 62,2 Tn)
3 Seaports (IDR 1,3 Tn)
17 Projects out of
Preparation Stage to
Construction Stage
Penambahan Lingkup Jalan Tol Depok Antasari
6.600
Makassar New Port
3.168
Pembangunan Pelabuhan Patimban
43.221
Pengembangan Pelabuhan Terminal Kijing
Pengembangan Pelabuhan Kupang
5.048
223
•
6 Airports (IDR 14,5 Tn)
•
•
4 Dam (IDR 7 Tn)
1 SEZs and IES (IDR 31,4 Tn)
2 Irrigations (IDR 5,7 Tn)
2 Clean Water & Sanitasionsi (IDR 72,9 Tn)
8 PSN Projects were successfully pushed to operated partially with
estimated investment value IDR 100,8 Trillion
•
1 Energy (IDR 196,9 Tn)
Status is a comparison of progress between December 2020 and June 2021
Source: Committee for Acceleration of Priority Infrastructure Delivery (KPPIP)
*) National Strategic Projects (PSN)