Antofagasta Results Presentation Deck slide image

Antofagasta Results Presentation Deck

Los Pelambres Expansion - Phase I 60,000 tonnes¹ of additional copper Optimise throughput within the limits of the existing operating, environmental and water extraction permits Increasing plant capacity from 175ktpd to 190ktpd Annual copper production will increase by an average of 60,000 tonnes¹ per year over 15 years Project 45% complete2, end 2020 ● 1 2 ● ● Project update - January 2021 ● ● ● Change of scope - enabling capex for future increase in desalination plant capacity from 400 l/s to 800 l/s to optimise capital expenditure Capital cost of $1.7 billion includes costs related to COVID-19 and change in scope to enable future expansion of desalination plant Project completion expected in H2 2022 Compared to production without the project. Averaging 40,000tpa in years 1-4 and 70,000tpa in years 5 to 15 Engineering, procurement and construction ANTOFAGASTA PLC 20