QALA SHALLOWS
DFS on Kimberley Reef
ROBUST DEFINITIVE FEASIBILITY STUDY³
"
Gold produced: 924,000oz
Steady-state production: 70,000oz p/a (9 years)
~2000 P
Ore Reserves: 4.03 million tonnes at 2.71g/t for 351,400 oz gold
Life-of-Mine: 17.7 years
RAPID PRODUCTION GROWTH
Critical infrastructure completed
Decline & box cut rehabilitation completed
☐
Mining blocks available by access
Established water supply infrastructure
Qalla Deeps
Received 7.5MVA power allocation with primary power substation
completed
Advanced infrastructure set up for rapid near-term production ramp-up
"We've got plenty of gold and even at 70,000 ounces a year, we
are only scratching the surface of what this ore body can deliver."
Michael Quinert, Chairman
ASX:WWI
-2000m
IN
COMPLETED
500m
WEST WITS
MINING
UNDERGROUND WORKINGS
KR Horison
850m
Qala Shallows
1850m
1100m
Qala Shallows Boxcut
LOM Decline System
UNDERGROUND
PRODUCTION PLAN
Existing Decline Slyping and Rehabilation
Early Stoping Panels Establishment
Two-level Ore Drive