Minas-Rio Impairment Considerations and Project Delivery slide image

Minas-Rio Impairment Considerations and Project Delivery

PIPELINE Current status and points of attention Key stats 66% 66% complete 76% cleared for pipe laying > 247 km ~50% of pipe laid 95% of 1,555 properties realised ~6,000 people at site FRONT 1 LICENCES FRONT 1 LAND ACCESS PROCUREMENT DELIVERY O Complete relocation of legal reserves ■ Conclude final arrangements in partnership with Minas Gerais Roads Agency (DER) & Nova Era Silicon ■ Finalise contract amendments with key pipeline contractors ■ Maintain the sense of urgency ■ Closely monitoring productivity and bottlenecks 16