Kidston Pumped Storage Hydro Project Kidston Hydro Project Schedule MCCONNELL DOWELL Stage 1: key works 20 May-2021 31 Dec-2021 Financial Close Genex | Green Energy, On Demand | Presentation PKP JOHN ANDRITZ HOLLAND ENGINEERED SUCCESS Overall Key Work Packages Turbine and Detailed design complete Generator 31 Dec-2022 manufacture 31 Dec 2023 Turbine and Generator installation 31 Dec 2024 Commencement Wises of access tunnel Dam Powerhouse Cavern Pit Transmission Commissioning dewatering line 18