Investor Presentaiton
8
TBS
Energi
Utama
Power Business
TBS Overview
Financial Performance
Mining Business
PT Gorontalo Listrik Perdana Sulbagut-1 Project
CFSPP Sulbagut-1 (2X50 MW)
North Gorontalo, Gorontalo Province,
Indonesia
•
Project Overview
Partnership Composition: TBS (60%), PT Toba Sejahtra (20%)[1],
Shanghai Electric Power Construction (SEPC) (20%)
PPA signed in July 2016 and Financial Close achieved in July
2017
Contract Period: 25 years
Project Cost: US$ 224 million
EPC Contractor: Shanghai Electric Power Corporation
Progress Updates (as of 31 December 2020)
Remarks
In-Progress
Land acquisition completed
All drawing and engineering documents has been completed and submitted by contractor.
Boiler, Turbine and Generator has been completed manufacture, and have arrived on-site
Procurement 18 out of 20 project shipments (major equipment) have arrived on site.
Subject
Status
Land Acquisition
Completed
Engineering
Completed
Boiler, Turbine, Generator
Completed
("BTG")
Procurement
Construction
In-Progress
•
Both Boiler #1 and Boiler #2 have completed Hydrotest
•
Main power building installation in-progress
www.tbsenergiutama.com
•
Both Turbine #1 and Turbine #2 have been installed and will continue in field work to connect
with the GeneratorView entire presentation