Project Execution Expertise Driving Efficient Capital Allocation
Project cost of select power plants set up by other
players in the industry
Power Project
Capacity
Project cost
1st COD
JPVL (Nigrie)
MW
1,320
INR Crore/MW $mn/MW²
Year
7.92
1.11
2014
Giral (Rajasthan)
250
7.69
1.08
2011
DB Power (Janjgir-Champa)
1,200
7.02
0.98
2014
INR 6.63 Crore¹/MW
Neyveli (Barsingsar)
250
7.00
0.98
2010
GMR EMCO (Warora)
600
6.25
0.88
2013
Adhunik (Padampur)
540
6.18
0.87
2013
Dhariwal (Chandrapur)
600
6.22
0.87
2014
Lanco (Amarkantak)
600
5.23
0.73
2009
Tata Power/DVC (Maithon)
1,050
5.24
0.73
2011
Aryan Coal (Kasaipalli)
270
5.00
0.70
2011
Lanco (Udupi)
1,200
4.67
0.65
2010
Vijayanagar
Vijayanagar
(2010):
600 MW @
INR 3.28 Crore/MW
(2000-2001): (~$0.46mn/MW)²
260 MW @
INR 4.34 Crore/MW
(~$0.61mn/MW)²
Ratnagiri
(2011-2012):
1,200 MW @
INR 4.60 Crore/MW
(~$0.64mn/MW)²
Barmer
(2010-2013):
1,080 MW @
(~$0.93mn/MW)²
JSW Energy
(1) High capital cost due to CFBC boilers for lignite based power plant
(2) USD/INR = 71.3 Source: RBI reference rate as of Feb 10, 2020View entire presentation