Ongoing Expansion Progress on track Cement Silo 1 Cement Mill Hopper Greenfield Expansion at Ujjain (Grinding Unit) 1.5 MTPA Additional Grey Cement Capacity Status Update Work is progressing as per schedule. Commissioning schedule - Nov-Dec'23 Capex YTD Sep'23 €232 Cr Bhoomi Pujan Cement Silo (MCS) Greenfield Expansion at Prayagraj (Grinding Unit) 2.0 MTPA Additional Grey Cement Capacity Status Update Foundation stone laid in Aug'23 & Orders for main equipments have been placed. Civil & mechanical contractors have been mobilized at site & civil work started. Capex YTD Sep'23 *61 Cr JKcement 10