Investor Presentation slide image

Investor Presentation

We have a policy of contracting major equipment upfront at fixed price mitigating concerns on capex cost inflation Secured Capacity Breakdown % Fully contracted (1) or Higher Capex already embedded in Investment decision edp Recent Auctions already incorporating higher bid prices (e.g. Spain Auction) ~90% Revising Bid prices in PPAs under negotiation and still shortlisted Major equipment partially contracted (2) ~10% Top tier customer for wind and solar equipment with recurrent orders of >1 GW/year both for wind and solar We have a strong position and a privileged relationship with suppliers, and we continue to monitor and manage disruptions to the supply chain Strong returns with spread to WACC >300 bps (1) WTG for wind projects; Modules; Trackers and Inverters for solar projects | (2). Capacity which has Major equipment partially contracted, but not fully Investor presentation 11