Investor Presentaiton slide image

Investor Presentaiton

DUPARQUET PEA SUMMARY $ FIRST MINING GOLD Key Assumptions LOM Operating Costs (US$/oz)(1) LOM Gold Price US$/oz US$1,800 Cash Costs (US$/oz) (2) US$/oz $751 Exchange Rate (C$:US$) 1.33 AISC (US$/oz)(3 ) (3) US$/oz $976 Production Profile LOM Capital Expenditures LOM Total Open Pit Tonnage Mt 282 Initial Capital C$M $706 Total Open Pit Ore Mt 43.6 Sustaining and Development Capital C$M $738 Open Pit Strip Ratio W:0 5.4 Net Closure Costs C$M ($6) Total UG Ore Mt 12 Estimated Salvage Value C$M ($36) Total Tailings Ore Total Tonnes Processed Throughput Mt 4.1 Economics - Pre-Tax LOM Mt 59.7 NPV at 5% D.R. C$M $1,073 tpd 15,000 IRR % 24.9% Mill Grade Mine Life g/t Au 1.51 Payback years 3.8 years Recovery LOM Metal Recovered years % 11 years Economics - Post-Tax LOM 89.5% NPV at 5% D.R. C$M $588 koz Au 2,595 IRR % 18.0% Average Annual Recovered koz Au 233 Payback years 4.8 years Operating Costs per Tonne LOM Mining Costs - OP C$/t mined $3.16 STRONG LEVERAGE TO GOLD PRICE UPSIDE Mining Costs - OP C$/t $20.85 Gold Price Mining Costs - UG C$/t $44.26 Processing Costs C$/t $10.59 G&A Costs C$/t Total Operating Costs C$/t $2.90 $78.60 23.2% Note: Further details can be found in the technical report titled "NI 43-101 Technical Report: Preliminary Economic Assessment, Duparquet Project, Quebec, Canada", dated October 20, 2023, as filed on SEDAR+ and on www.firstmininggold.com Pre-Tax NPV5 Pre-Tax IRR After-Tax NPV 5% After-Tax IRR 5% US$1,600 C$621 M 17.1% C$310 M 12.1% US$1,800 US$2,000 US$2,200 C$1.07 B 24.9% C$1.53 B C$1.98 B 32.0% 38.6% C$588 M 18.0% C$859 M C$1.12 B 28.0% TSX: FF | OTCQX: FFMGF | FRANKFURT: FMG | www.firstmininggold.com | 26
View entire presentation