TRANSGRID - GROWTH OPPORTUNITIES (I)
From mid-2020 under the National Electricity Rules there is a requirement to progress the regulatory process and preparatory work for
actionable ISP projects
AEMO ISP 2020
Trans Grid Network Opportunities
Modelled Cost
Delivery
Target (1)
2018-2023 capex allowance
$1.2bn
N/A
Committed
QNI Minor
Actionable
(2)$0.2bn
2021-22
CENTRAL-WEST ORANA ENERGY ZONE
Narrabri
voltage control
I
ARMIDALE
New capacity
to Gunnedah
NEW ENGLAND ENERGY ZONE
MEDIUM-LARGE
QUEENSLAND-NSW INTERCONNECTOR
QUEENSLAND-NSW INTERCONNECTOR UPGRADE
VNI Minor
(3)$0.1bn
Backup supply to Broken Hill
2022-23
Busbar upgrades
bat Broken Hill
Project EnergyConnect (PEC)
(4)$2.0bn
2024-25
DUBBO
Voltage support in Greater Sydney
HumeLink
(3)$2.1bn
2025-26
New capacity
7
near Beryl
Supply to Macarthur area
Central-West Orana REZ Transmission Link
$0.7bn
2024-25
Molong-Orange North
capacity increase
Supply to South-Western Sydney Growth areas
VNI West (Kerang Route) (4)
(3)$2.4bn
2027-28
Voltage control
at Parkes
BURONGA
New capacity
near Orange
Total
$7.3bn
I
Capacity increase at
Darlington Point
O
Supply to North-Western Sydney growth area
SYDNEY
GANNASY
POWERING SYDNEY'S FUTURE
Preparatory Activities Required
DARLINGTON
POINT
Wagga Wagga North
capacity increase
HUMELINK
ENERGYCONNECT
QNI Medium & Large
$3.3bn
New England REZ Network Expansion
(5)$1.3bn
2032-33 to
2035-36
2030s
DINAWAN
WAGGA
WAGGA
CANBERRA
Voltage support
in the ACT
Wagga-Yass transfer capacity increase
SOUTH-WEST ENERGY ZONE
TUMUT
Upper Tumut-Yass transfer capacity increase
North West NSW Network Expansion
(6)$0.9bn
2030s
Jindera-Wagga transfer capacity increase
VICTORIA-NSW INTERCONNECTOR UPGRADE
Total
$5.4bn
VICTORIA-NSW INTERCONNECTOR WEST
Total ISP Modelled Projects
$12.9bn
NSW Map Source: Trans Grid,
Transmission Annual Planning Report 2020
(1) AEMO 2020 ISP (2) Contingent Project Application (CPA) Approved 28 April 2020 (3) RIT-T process underway
(6) Includes combined costs for Stage 1,2 & 3
Spark Infrastructure I Investor Presentation | February 2021
(4) CPA process commenced 9 October 2020.
(5) Includes combined costs for Stage 1 & 2