GAIL Financial Overview

Actual Capex & Capital Commitment in Major Projects Commissi Lengths of oned Approved Name of Projects Pipelines Expected Completion Date length Cost Capital commitment Actual Capex up (Km) (Km) to 31.03.2022 Dhamra-Angul P/L 400 31st December 2022 1,933 1,930 1,653 Dobhi-Durgapur P/L 500 359 30th June 2022 2,433 2,377 2,223 Bokaro-Angul P/L 670 474 30th June 2022 3,048 2,670 2,395 Durgapur-Haldia P/L* 335 30th June 2023 1,740 1,448 989 Barauni Guwahati P/L* 729 30th June 2023 3,060 3,458 2,679 Dhamra-Haldia P/L* 253 30th June 2023 1,031 785 356 KKBMPL - II P/L* 891 579 28th Feb 2025 5,909 4,089 3,566 Srikakulam-Angul P/L 744 31st July 2023 2,658 1,517 627 Mumbai-Nagpur-Jharsuguda P/L 1,755 14th May 2023 7,844 3,800 2,283 Major PC Projects: Propane Dehydrogenation & 500 KTA NA 7th April 2025 8,255 5,683 248 Polypropylene Project (PDH-PP), Usar Polypropylene Project (PP), PATA 60 KTA NA 31st January 2024 911 931 202 *Subject to availability of hindrance free Rou