Managing cost inflation Price escalation clauses at Paint and Final Assembly Systems Protection against inflation for long-term projects ■ Link price to material and personnel cost indices ■ Formula proposed by VDMA (association of mechanical and plant engineering industry) ■ All indexes are publicly available and are published monthly Applied in large contracts since 2022 Price escalation clauses formular = Price P0 x (Share of labor cost x L1/LO + Share of purchased parts x M1/M0 + Share of raw material1 x Sa1/Sa0 + Share of raw material2 + Sb1/Sb0 + ...) PO: Price at time of order negotiations; LO,L1,MO,M1,Sa0, Sa1,...: Index at time of order negotiation and cost incurrence Large contracts at Paint and Final Assembly Systems include price escalation clauses www.durr-group.com © Dürr AG, CCI, Investor Relations Presentation, May 2024 DÜRR GROUP. 55