Antofagasta Results Presentation Deck

Los Pelambres Expansion - Phase 1 52% complete Desalinated water system Marine Works progress over 60% in Discharge and Intake tunnels Desalination plant civil works close to completion ● ● Growth projects update Concentrator New flotation circuit being erected • Stockpile expansion completed ● Zaldívar Chloride Leach 3600001 76% complete Chlorine corrosion-resistant materials installed in three of four solvent extraction (SX) trains New reagents facilities and washing ponds on schedule Centinela Esperanza Sur Pit ● ● ● Pre-stripping completed in July First autonomous trucks arrived in June Operating autonomy tests start in September Centinela Second concentrator ● ANTOFAGASTA PLC ● EIS update approved and SERNAGEOMIN critical permits granted Started detailed engineering for concentrator EPC Bidding processes for new tailings storage facility, water pipeline and other infrastructure are in progress 24