Roadmap of NPP Site Feasibility Study
Year
2010
2011
2012
2013
Pre-Survey
Site Survei:
Regional dan
Near Regional
Note:
Regional Analysis:
map scale 1/500.000
- 1/100.000
Near Regional:
map scale 1/50.000
- 1/25.000
Site Vicinity:
map scale 1/5.000
Site Evaluation:
map scale 1/1.000 -
1//100
Site Survey:
Site Vicinity
and
¡Site Characterization
(Evaluation)
Pre-Operational
Land Acquisition
Land Clearing
Access Road
Harbour
SITE MONITORING (continue)
(seismicity, GPS geodetic, meteorology, environment, oceanography, etc)
SDR (18 months)
SER, SDI, Intg'd FS
Site Permit
EIAR,
EIAR Approval
Emergency Preparadness
Spatial Planning for NPP
BIS
Draft of Master Plan for NPP
Cost 1: 25%
Not included in the financing scheme
Cost 2: 67%
Cost 3: 8%
Total: 100%