Investor Presentaiton
FY23 Capital and investment expenditure
$ million
Growth capex
Regulated
Description of major projects
FY23
FY22
Western Outer Ring Main (WORM), Winchesea
Compressor; Access Arrangement Allowed
Expenditure
242
80
68
Non-Regulated
- East Coast Gas
- West Coast Gas
- Electricity Generation and Transmission
East Coast Grid Stage 1, Kurri Kurri Gas Lateral
172
129
Northern Goldfields Interconnect
300
217
-
- Customer contribution projects and others
Dugald River Solar Farm; Gruyere Power Grid
VIC estate, road and rail projects
113
76
18
33
845
523
Total growth capex
SIB capex
- Asset Lifecycle capex
- IT Lifecycle capex
Total SIB capex
Foundation capex
- Technology and Other capex
- Corporate Real Estate
161
123
32
7
193
130
10
18
22
17
Total Foundation capex
32
35
Total capital expenditure
- Acquisitions and Investments
Total capital and investment expenditure
1,070
689
110
587
1,180
1,276
The capital expenditure shown in this table represents payments for property, plant and equipment as disclosed in the cash flow statement, and excludes accruals brought forward from the prior period and carried forward to the next period. Represents stay-in-
business capital expenditure not recoverable from customers and/or regulatory frameworks.
APA FY23 Results Investor Presentation