Investor Presentaiton slide image

Investor Presentaiton

20 PERMIT SUMMARY Verde currently has full rights to mine 482,800 tpy (since it holds mining Concessions/Permits and Environmental Licenses) and has submitted joint mining and environmental applications for an additional 2,500,000 tpy. Mining (tpy) Mine Pit Fully Permitted to Produce (tpy) Granted Pending 1 2 3 Total 233,000 200,000 233,000 О 200,000 25,000,000 Granted Environmental (tpy) Pending 233,000 2,600,000 0 0 49,800 49,800 2,500,000 49,800 2,500,000 482,800 The amount that is fully permitted supports the Company's target for 2021. 482,800 27,500,000 2,882,800 2,500,000 VERDE AGRITECH
View entire presentation