Investor Presentaiton
Plan to transform our options
into commercial solutions
Stage 2 (feasibility in 2020 or earlier)
TECHNOLOGY
PROJECT
GAS
NSW | Gas peaker (500MW)
RENEWABLES
500MW
B
DEMAND
Up to 50MW
RESPONSE
Stage 3 (feasibility in 2021 or earlier)
BATTERY
Liddell | 250MW
**
RENEWABLES
250MW
DEMAND
RESPONSE
Up to 30MW
2017
2018
2019
اليم
Announced closure date for Liddell
Project delivery
Project delivery
Progressive trials & pilots
Delivery
agl
Project delivery
Progressive trials & pilots
2020
2021
2022
2023
2024
Delivery
Approved
AGL is considering the feasibility of pumped hydro assets in New South Wales in Stage 2 & 3
FID (conditional¹) Offtake approved
1. Conditional Final Investment Decisions will be subject to planning approval, EPC contract and connection agreement.