Laos Sustainability Report
16
Guaranteeing project quality
O Quality management system
PowerChina adopts the "1+2+3"
management model in the Nam Ou River
hydropower stations project in Laos,
meaning that centering on the priority
of onsite control, the basin company
monthly control and supervision as well
as the daily control of supervision, design
and construction units are incorporated;
importance is attached to "the three
links" of visits of the construction site,
communication with all participating
construction units, and dialogue with
employees of the project department;
onsite control is enhanced and refined
management is implemented for the
project, achieving overall streamlining and
control of the construction of level-2, level-5
and level-6 hydropower stations of the
Phase I project, thus effectively ensuring
the smooth attainment of various node
targets.
Onsite quality control of Nam Ou River Level-3 Hydropower Station
In the construction of Nam Ou River Level-3 Hydropower Station, the principle of total
quality control was followed to fully strengthen onsite quality control. Participating
units established their respective quality assurance system and quality management
system, and specified quality responsibility and quality management requirements for
their respective departments and positions. Monthly quality check was organized for all
participating units which resulted in monthly quality inspection bulletin. In a period of
one year, 489 units of the main project were inspected and accepted, with an acceptance
rate of 100%; among them 440 units were rated "excellent", accounting for 90%. There
was always solid quality management and onsite quality control.
Projects of ingenuity
Since it entered the Laotian market more
than 20 years ago, from constructing
roads to the site of Nam Leuk
Hydropower Station by No. 15 Bureau
of SINOHYDRO under PowerChina to
helping the Laotian government build the
"Southeast Asia Battery", the company
has contracted over 30 projects, involving
construction of water conservancy,
roads, railways, bridges and municipal
engineering construction.
The Nam Ou River cascade hydropower
stations project in Laos is the project
for which a Chinese company has the
development right of the basin of an
entire river overseas for the first time.
It is also the first investment project
implemented by PowerChina in executing
its strategy of integrating the entire
industry chain overseas by actively "going
global" under the guidance of the "Belt
and Road" initiative. The project consists
of 7 cascade hydropower stations
with a total installed capacity of 1.272
million kilowatts, average annual power
generating capacity of 5 billion kilowatt-
hours for years, and a total investment
of USD2.733 billion. Level-2, level-5 and
level-6 Hydropower Stations of the first
phase have been completed and put into
operation, and level-1, level-3, level-4
Power Construction Corporation of China
and level-7 Hydropower Stations of the
second phase were started to construct
in April 2016 and all are expected to be
completed and to start power generation
in August 2020. As the key power source
of the power grid for Northern Laos, since
its operation started, the Nam Ou River
cascade hydropower stations project
has relieved local power shortage,
and provided stable and reliable
安金经济高效
Acceptance rate of 100%
Rated "excellent",
accounting for 90%
power support for local infrastructure
improvement and industrial development.
The Nam Ou River cascade hydropower
stations still under construction will further
facilitate Laos' infrastructure upgrade
and transformation, boost the industrial
development of surrounding areas, and
create a large number of employment
opportunities.
Nam Ou River Level-2 Hydropower Station
运营项目
PROJECTS IN OPERATION
中国
CHINA
宁海
警洱市
糰扎波:
思茅港
惠民
小勤共
**
/**
孟糖
6诺
关潢
六级电站
NAM Ou 6 HPP
缅甸
MYANMAR
五级电站
NAM Ou 5 HPP
**
動態
A
香香
**
ASMR
二级电站
NAM Ou 2 HPP
万荣
#
帕市
越南
VIETNAM
Pohong
LAOS
**
am
纳案
老挝南欧江流域梯级水电站项目(一期)
Nam Ou River Basin Hydropower Project in Lao PDR
『普蓋包
万象
泰国
THAILAND
在建项目
PROJECTS UNDER CONSTRUCTION
七级电站
NAM Ou 7 HPP
四级电站
NAM Ou 4 HPP
三级电站
NAM Ou 3 HPP
一级电站
NAM Ou 1 HPP
Plane position of Nam Ou River cascade hydropower stations (7 levels)
"PowerChina is a central enterprise with a great tradition and capable of
fighting tough battles. It is the spirit of the iron army that creates such an
excellent team, which is a key enterprise in serving the 'Belt and Road'
construction."
-- Meng Jianmin, Vice Director of State-owned Assets Supervision and
Administration Commission of the State Council
"The Nam Ou River project plays a critical role in promoting local economic
and social development. It has become a star project and important livelihood
project in Northern Laos boasting significant influence and popularity, setting a
good example for other external investment projects."
--Zonse Siphandone, Deputy Prime Minister of Laos
老挝南欧江流域梯级水电站项目(二期)
Nam Ou River Basin Hydropower Project in Lao PDR
17
Laos Sustainability ReportView entire presentation