PTTEP Project Details and Financial Performance
Projects Details | Thailand
1
Arthit
2
B6/27
Sales Vol Gas
Sales Vol Liquid
Project Name
Status
Phase
Participating Interest* (%)
Latest Status
(MMSCFD)
(KBPD)
OP
Production
PTTEP
80%
280
15
Ensure gas delivery at the highest DCQ
Chevron
16%
MOECO
4%
OP
gp
Production
PTTEP
100%
PTTEP
Prepare for decommissioning activities
The Final Decommissioning Plan (FDP) and Decommissioning Cost
Estimation (DCE) were approved by DMF
.
12
Normal operations
JV
Production
3
B8/32 & 9A
PTTEP
25.00%
40
40
Chevron
51.66%
MOECO
16.71%
KrisEnergy
4.63%
Palang Sophon
2%
OP
Production
4
Bongkot
PTTEP
66.67%
508
17
TotalEnergies
33.33%
OP
Production
5
G12/48
PTTEP
66.67%
9
TotalEnergies
33.33%
JV
6
Contract 4 (Pailin)
M
Production
PTTEP
60%
405
15
Chevron
35%
MOECO
5%
JV
7
E5
M
Production
PTTEP
20%
7
ExxonMobil
80%
Note: *
**
PTTEP denotes respective PTTEP subsidiaries participating in the project
Sales volume represent average volume for 100% of the project during 3M2023
***
Status: OP PTTEP operatorship/JOC = PTTEP joint operatorship/ JV = PTTEP Joint Venture Partner
**** DCQ Daily Contractual Quantity
33
The remaining block was ended on 7 Mar 2023 and transitioned to G2/61
under PSC.
Normal operations
Ensure gas deliverability level at DCQ.
On-going drilling additional development wells activities.
Maximize gas potential at CDC level.View entire presentation