CoreCivic Lease Agreements and ESG Strategy
Project Overview
•
In September 2020, CoreCivic was selected as the preferred developer for two of the three New Facilities, which includes the Elmore County and Escambia County Correctional
Facilities, as described below
Overview of New Facilities*
Elmore County Correctional Facility
Escambia County Correctional Facility
Expected Costs and Timeline
Payment
Construction Timeline
Estimated Construction Costs (subject to change)
•
The Facility will provide minimum-medium custody for ADOC's inmate population
•
This facility will be larger than the Escambia County Correctional Facility and contain ADOC's special
services (e.g. medical, mental health, aged care, and inmate reception)
The Facility will provide minimum-medium custody for ADOC's inmate population
Lease payments from ADOC, subject to annual appropriations from the Alabama Legislature
•
Approximately 42 months
Elmore County Correctional Facility: approximately $508.3 million
Escambia County Correctional Facility: approximately $266.5 million
Combined, the two New Facilities will provide approximately 7,000 beds for ADOC
*There is a third facility that was awarded to another Developer.