NHPC Capacity Addition and Financial Overview
PHYSICAL SNAPSHOT
•
Incorporated in 1975 with authorised capital of Rs. 200 crore,
the present authorised capital is Rs.15000 crore (Paid Up
Capital Rs.10,045 crore)
•
Mini-Ratna Category-I PSU (since Apr-08)
• Established track record, strong operational performance and
in-house engineering capabilities
• Involved across the entire chain of hydro power project
development - from concept to commissioning.
Presence across 14 states & 2 UTs.
4
Ratle Kwar
Kishanganga
Chutak
Uri I
Nimoo Bazgo
Kiru
Uri II
Pakal Dul
Salal
J&K
Sewa II
Chamera I
Dulhasti
Baira Siul
Chamera II
HP
Parbati II
Subansiri
Chamera III
Rangit-IV Lower
Parbati III
Punjab
Haryana
Delhi
UttaranehaDhauliganga I
Teesta V
- Tanakpur
Kalpi
Jaisalmer
300 MW
Solar
600 MW
Solar
Rajasthan
Jharkhand
Gujarat
Madhya Pradesh
Manipur
Mizoram
West Bengal
Chhattisgarh
Tripura
Odisha
Teesta VI
Sikkiml
Arunachal
Pradesh
Rangit
Dibang
Uttar Pradesh
Assam
Bihar
Nagaland
-Loktak
Maharashtra
Andhra
Pradesh
Indirasagar
•
⚫ 15% share of installed hydro-electric capacity in India (6,971
MW out of 46,850 MW*).
Omkareshwar
• Consultancy business.
⚫Power trading business.
Solar, Sanchi
Theni/Dindigul
Exposure to international business opportunities.
Omkareshwar
Floating Solar
Ground Mounted
Karnataka
Tamil Nadu
Kerala
* Source-CEA as on 31.03.2023
Teesta Low
Teesta Low
Dam - IV
Dam - III
Ganjam
100 MW Solar
Operating power stations (7,071MW)
Projects under construction (10,515 MW)
Note Map Not To Be Scaled
7071 MW installed capacity (6971 MW Hydro & 100 MW Renewable Energy) through 24 power stations
एनएचपीसी