Investor Presentaiton slide image

Investor Presentaiton

Divestment of hidaka Project Hidaka COD: March 2018 Project Details Business Type Project Owner : Solar power plant : SS Hidaka No Mori (GK Company) SERMSANG POWER CORPORATION Investment Type Investment Percentage Location Installed/PPA MW : Through SEG, as TK Investor, under GK-TK Investment Structure : 86.9% : Hokkaido, Japan : 21/17.0 MW Power Purchaser : Hokkaido Electric Power Company Limited Purchase Price Purchase Term : Under Fit Scheme of JPY 40/KWh : 20 years SSP 100.0% summary detail Selling Price 2,800 mJPY (exclude fees -1.5%) Partner Initial Investment 1,267.2 mJPY SEG SMS MS 86.9% 9.7% 3.4% Expected cash return ~2.4x SS Hidaka No Mori Expected equity IRR Plan for use of proceed -20% • Equity injection for Leo2 project by end of this year. • Capital for others project on hand and working capital. 5
View entire presentation