FIELDWORK ACTIVITIES ON PROJECT SITE The activities carried out covered 44 wells and 16 boreholes in 44 villages are as follows; •Use of topographic maps: Topographic maps covering the area under consideration were used as guide to Communities under consideration and determination of the distance between them. •Determination of borehole co-ordinates using GPS: A GPS was used to determine the co-ordinates (Longitude and Latitude) and altitude of the water point. •Determination of piezometric (static) water level: Deep meter was used to determine the static water level. ⚫Determination of total depth: Total depth of well/borehole is determined using depth meter. 6