Business Performance Review
Future Capacity Expansion Plan
Expansion Type
Division
Location
Status & Planned Capacity
Operational
Timelines
208 KL (Under Construction)
FY24
Brownfield
API/Intermediate
Ankleshwar
Planned addition of 280KL-300KL
FY25-FY26
Brownfield
API
Dahej
Planned addition of 220KL-240KL
FY24-FY26
Greenfield
API
Solapur
CTE received for 1,000MT
~500 KL capacity will be operational
by FY26
FY26
Total Reactor Capacity Expansion Plan (KL)
2,405
Capacity
1,792
1,456
Progress
by Year
1,198
765
FY22
FY23
FY24E
FY25E
FY26E
18
✓ Backward Integration plant at Ankleshwar of
208KL is under construction.
✓ Engineering work started for construction at
Solapur Plant of 200KL (Phase 1).
✓ Solapur's further capacity expansion will be
calibrated as per the volume demand
Є Glenmark
LIFE SCIENCESView entire presentation