Business Performance Review

Future Capacity Expansion Plan Expansion Type Division Location Status & Planned Capacity Operational Timelines 208 KL (Under Construction) FY24 Brownfield API/Intermediate Ankleshwar Planned addition of 280KL-300KL FY25-FY26 Brownfield API Dahej Planned addition of 220KL-240KL FY24-FY26 Greenfield API Solapur CTE received for 1,000MT ~500 KL capacity will be operational by FY26 FY26 Total Reactor Capacity Expansion Plan (KL) 2,405 Capacity 1,792 1,456 Progress by Year 1,198 765 FY22 FY23 FY24E FY25E FY26E 18 ✓ Backward Integration plant at Ankleshwar of 208KL is under construction. ✓ Engineering work started for construction at Solapur Plant of 200KL (Phase 1). ✓ Solapur's further capacity expansion will be calibrated as per the volume demand Є Glenmark LIFE SCIENCES