Construction activities continue to progress with design reaching 99.6% completion while international
procurement 99.8% completion
Pyrite Plant
Acid Plant
Site works completed during the quarter include:
• Pyrite Plant: Construction activities ahead of schedule with ongoing structural, mechanical and electrical works. Pre-commissioning will take place in May
Acid Plant: Construction activities ahead of schedule, with ongoing structural, mechanical and electrical works. Pre-commissioning will take place in June
•
•
Chloride Plant: Construction activities are on schedule, with ongoing structural, mechanical and electrical works. Pre-commissioning will take place in June
Wetar Barge Jetty: Construction is ongoing with structural, mechanical and electrical works ongoing. Wet commissioning will take place in July