Investor Presentaiton
Ongoing Capex and Upgrades
Brookfield
India Real Estate Trust
Rs 2.6 billion of capex projects underway across new tower developments and upgrades to
existing towers. Capex including interest during construction to be financed through debt
ONGOING PROJECTS (1)
Asset Upgrades/Tenant Improvements
Kensington
G2
N1
N2
K1
Sub Total
New Development
K1 - Mixed Use Development
Sub Total
Total
ESTIMATED
COMPLETION DATE
PENDING COSTS
(MILLIONS)
Q1 FY2024
Q1 FY2024
Q2 FY2024
Rs 68
62
93
Q2 FY2024
70
Q1 FY2024
7
Rs 300
Q3 FY2026
(1) Capex budgets for asset upgrades and tenant improvements:
- Asset Upgrades: Façade and canopy at Kensington; food court and gym at G2; landscaping, external developments and ongoing fitouts at N1;
and landscaping and façade upgrades at N2.
- Tenant Improvements: At Kensington, G2, N1 and K1.
2,323
Rs 2,323
Rs 2,623