Expansion Plans and Financial Overview

Expansion -Project Status Expansion Additional Capacity Status Update Greenfield Expansion at Panna (IU) with Hamirpur(GU) Grey cement plant of 4 MnTPA & WHR power generation of 22 MW Work is in progress as per schedule - Panna - Cement Grinding & Packing System has been successfully commissioned and first dispatch done on 2nd Nov 22 .Clinkerisation process likely to start soon. Hamirpur - Work is in advanced stage .Unit is likely to commission shortly. Expenditure as on date is funded by borrowing of Rs 1218 crores and Rs 1326 crores from Internal Accruals. CAPEX till YTD Sep'22 JKcement Expected Date of Completion Rs.2544 crores Dec'22 15