CAPITAL COST ESTIMATE
•
The capital cost estimate includes direct, indirect
costs, freight, professional services, taxes and
contingency.
The DLE plant will be supplied and commissioned by
Sunresin, Anson's technology partner.
Worley group have estimated the capital costs for all
above ground facilities.
Capital cost estimate accurate to within +25%/-15%.
The new production site and updated project layout
has resulted in significant capex savings over PEA by
reducing pipeline required from ~40kms to ~5km.
1 - ASX Announcement 25 August 2022.
ANSON
RESOURCES
Capital Item
US$m
Direct Capital Costs
275.2
Indirect Capital Costs
126.0
Other Costs
17.8
Production and Disposal Wells
22.0
Project Capex
441.0
Owners Costs
31.3
Contingency
22.8
Total Capital Costs
495.1