Inspiring Tomorrow - Corporate Presentation
ON TRACK TO BE COMPLETED BY 2025
EPC costs of ~$6.2 Bn (1) with Additional $0.3 Bn Pre-Operating Expenses
بروج
772
Borouge
Key Construction
Packages
Pre Start-up
Operating Expenses
Utilities, Offsites and
Early Works
Cracker Unit
Polymers Unit
XLPE-2
Overview
Costs (mainly personnel)
leading up to the completion
of the plant and
commissioning in 2025
Utilities systems, wastewater
and sewage treatment, tank
farm and storage, marine
facilities and demolition, site
preparation and grading,
security fencing, site access
and gates including
modification / alteration to
highway
Ethane cracker, including the
associated steam utilities
Cost
~0.3 Bn
Total Project Cost
Source: Company Information
1)
2)
59
Also includes FEED study, project management, and contingency costs
Excludes capitalized interests
Corporate Presentation | April 2022
~$6.5 Bn (2)
Polymers package
encompassing PE 6 and
PE 7 and 1-Hexene
New XLPE-2 unit
~$6.2 Bn (1)