FUKUSHIMA Lessons Learned

Project roadmap (3/3) TEPCO accepts the solution All equipment delivered at J-Village Start of tests with low active seawater Apr. 8 Design Tps de contact 15 May Equipment delivery Start of active operation Desalinated treated water recycled to cool reactors End of AREVA'S intervention on site May 17 June Jun. 8 Jun. 17 Jun. 26 July Jul. 6 Laboratory tests Pilot scale tests at Kawasaki Site construction Tests & commissioning Construction in RW building Commissioning FUKUSHIMA Lessons Learned IAEA January 2013-- p.6 A AREVA