Renewable Energy, On Tap

Project Construction Schedule Stage 1: key works 20 May-2021 31 Dec-2021 Financial Close 773F07 P282 Overall Key Work Packages Detailed design complete 31 Dec-2022 Kidston Pumped Storage Hydro Project PATTEL'S OVER SIZE Turbine and Generator manufacture 31 Dec 2023 Turbine and Generator installation 31 Dec 2024 Commencement Commencement of Commence Powerhouse Pit Transmission of access tunnel Wises Dam dewatering line Cavern Excavation Genex Renewable Energy, On Tap | Investor Presentation Energisation 15