Investor Presentaiton
ANNUAL REPORT
P
Private Power and Infrastructure Board
ANNUAL REPORT
Private Power and Infrastructure Board
framework (i.e. Policy Framework for Power Generation 2021) keeping in view the investors' friendly
regime at one end and affordable electricity for masses at large through bringing-in market
competition.
There are various important bipartite and tripartite activities involved in processing of a power
generation project such as tariff determination, land acquisition, generation license, environmental
clearance, IA, PPA, WUA, CSA, TSA, FSA etc which are interdependent on each other and if this cycle of
activities is disrupted by any single activity, it impacts on the overall chain thus disturbing the project
timelines. In view of the above, although PPIB achieved significant progress in advancing and
implementing upcoming IPPs, however, some potential force majeures beyond the control of project
companies/sponsors hampered the overall development pace of few projects. However, in all such
cases, PPIB referred matters to the Board and extensions in achievement of various milestones which
include issuance of LOI/LOS/FC or RCOD were solicited while remaining within the legal/policy
framework and purely on the basis of merit. The projects which were delayed in accomplishing various
critical tasks due to multiple reasons are outlined as follows:
Project Description
660 MW Thar coal based
Engro Powergen
330 MW Thar coal based
ThalNova Power Project
330 MW Thar Coal based
Thar Energy Limited
Power Project
1320 MW Thar coal based
Shanghai Power Project
300 MW Imported Coal
based Gwadar Power
Project
Brief description of delay
The project was required to achieve COD by June 2019 however, COD
was achieved on 10th July 2019 due to the process of extensive testing.
Nevertheless, project had already started generating electricity from
both units (each comprising 330 MW) in March and April 2019
Project is behind the schedule and not likely to achieve COD in Mar-21.
Delays attributed to factors including outbreak of COVID-19 pandemic.
Other factors include Sinosure, macroeconomic situation, delays in
coal availability.
Project is behind the schedule and not likely to achieve COD in Mar-21.
Delays attributed to factors including outbreak of COVID-19 pandemic.
Other factors include Sinosure, macroeconomic situation, delays in
coal availability.
The Project is facing issues with regards to water allocation and
execution of Water Supply Agreement with Government of Sindh
because of which extensions in achievement of FC have been granted
by PPIB with the approval of PPIB Board. Such pause may also impact
on the overall progress of the project. COIVD-19 factor may also cause
disruption project development as potential force majeure.
Furthermore, hesitation from Chinese lenders and Sinosure for
financing the project is also causing delays.
Faced delays in issuance of LOS on part of tariff determination, land
acquisition, signing of PPA and grid interconnection & transmission
infrastructure issues. However, after partial resolution of some of the
issues, PPIB issued LOS to the Project on 23rd August 2019. Thereafter,
project is again facing delays regarding execution of Quad-partite
PPA. PPIB is coordinating with all the concerned stakeholders for early
resolution of the issues enabling to issue PPA and IA which are
pre-requisites for declaration of FC. In this regard, PPIB has twice
extended FC date with the approval of Board. The outbreak of
COVID-19 is also feared to further impact on the progress of project.
Project Description
330 MW Thar coal based
Siddiqsons Power Project
1320 MW Thar coal based
Oracle Power Project
1263 MW RLNG based PTPL
Project
700 MW Azad Pattan
Hydropower Project
1,124 MW Kohala
Hydropower Project
Brief description of delay
The Project is facing issues with regards to water allocation and
execution of Water Supply Agreement with Government of Sindh
because of which extensions in achievement of FC have been granted
by PPIB with the approval of PPIB Board. This delay may also impact on
the overall progress of the project. COIVD-19 factor may also cause
disruption in project development as potential force majeure.
Project is delayed due to following major reasons:
PPIB Board had in-principle approved issuance of NTP and LOI to the
sponsors, however, Sponsors could not meet certain technical, financial
and legal requirements in their proposal as per Power Policy 2015 and
applicable Guidelines for issuance of NTP and LOI. Renewed consents of
Power Purchaser (CPPA-G) and NTDC are required as earlier issued
NOC/Consents stipulated COD in December 2019 have expired. Fresh
approvals of JEWG, JCC of the CPEC and ECC of the Cabinet are also
required before processing new proposal of the project.
Project is facing delays mainly due to COVID-19 adverse implications and
non-execution of agreements as a result, certain other activities/tasks
dependent thereupon are also encountering delays.
Project is facing delays mainly on part of non-execution of project
agreements.
Project is facing delays in advancing due to factors which include but
not limited to Environment Flow matter and non execution of project
agreements.
Note: Outbreak of COVID-19 is anticipated to impact the majority of ongoing IPPs, however, IPPs which
are at advance stages of construction or about to start construction are more likely to be affected.
17
18View entire presentation