Mount Morgans - Project Infrastructure Capital Feasibility Study Total Project Infrastructure Capital of A$172M, but is Less... • . . New 2.5Mtpa CIL treatment facility and associated infrastructure A$134M Capital Cost Build adjacent to Jupiter Pit Other infrastructure, including: • New accommodation village (A$21M) • Mine service facilities at Westralia and Jupiter (A$7M) Communications (A$4M) • Roads & Earthworks (A$4M) Latest estimate received post Feasibility Study reduces capital to A$157M DACIAN GOLD LIMITED/daciangold.com.au 14