Vogtle Unit 4 Direct Construction & Major Milestones
(Direct Construction is Bechtel's Scope of Work)
Start Integrated Flush
Main Control Room
Ready for Testing
Jan-21
Feb-21
Mar-21
Apr-21
May-21
Jun-21
Jul-21
Aug-21
Sep-21
Oct-21
Structural Integrity /
Integrated Leak Rate
Tests Complete
Initial Energization
Nov-21
Dec-21
Start Open
Vessel
Testing
Jan-22
Feb-22
Mar-22
Apr-22
May-22
Jun-22
Jul-22
Aug-22
Sep-22
CUMULATIVE %
100%
O
Unit 4
In-Service
90%
O.
Start Fuel Load
80%
O
Start Hot Functional Testing
O.
Start Cold Hydro Testing
Blue Circles:
September 2023 Benchmark
I Direct Construction Monthly % Complete
Direct Construction Cumulative % Complete
Estimated September 2023 Benchmark Scenario
Estimated December 2023 Benchmark Scenario
9
Milestone bars and lines represent the range of potential start dates for each milestone with the left side of each indicating currently targeted start dates under the September 2023 benchmark and the right side indicating start dates expected to be necessary for December 2023 benchmark
Oct-22
Nov-22
Dec-22
Jan-23
Feb-23
Milestone Dates
50%
Red Circles:
December 2023 Benchmark
Milestone Dates
40%
Mar-23
Apr-23
May-23
Jun-23
Jul-23
Aug-23
Sep-23
Oct-23
Nov-23
Dec-23
60%
70%View entire presentation