Investor Presentaiton
South Africa Block 11B/12B
EPS Development Progressing
Assessing Early Production System (EPS) with existing nearby infrastructure
•
Preparing Field Development Plan, Environmental Application and Production
Right Application for submission by September 2022
Final Investment Decision (FID) targeted for 2023
•
First production targeted by end of 2025
Full Paddavissie Fairway development expected as domestic gas market expands
Wells
SPS
SURF
Riser
FA
Block 11B/12B
Block 9
WD
1700m
Well
Slide 10
PLET
Well
Manifold
Tee for future
CPF Connection
Well
119 km
WD 105m
FA Platform in Block 9.
Pipes to shore
FA Platform
Mossel Bay PetroSA GTL plant/
Eskom power plant
Subsea Cable
AE
AFRICA
ENERGY
GTL/Power Plant
90 km
SPS Subsea Production System
SURF - Subsea Umbilicals, Risers Flowlines
GTL - Gas-to-Liquids
PLET - Pipeline End Termination
CPF - Central Processing Facility
Africa Energy | March 2022View entire presentation