NHPC Financial Highlights & Renewable Energy Projects
NHPC Standalone Projects Under Clearance
32
Installed Design
S.No.
Projects
4
Sawalkot
(6x225+1x56)
UT of J&K
Capacity Energy
(MW) (MUs)
1856
Cost
(In Crore)
Status
& PL
7995
22704.80
(Completion)
•
MOU has been signed between NHPC Ltd. and JKSPDCL on 03.01.2021.
•
5
Uri-I Stage-II
(2x120)
240
929
2140
(Apr❜22)
UT of J&K
Total
5996
24159
67084.19
एनएचपीसी
NHPC
•
•
•
.
.
•
•
The project shall be executed by NHPC on BOOT basis for the period of 40
years.
Agreement for handing over / taking over signed between NHPC and JKSPDC
on 11.12.2021 & NHPC has taken over the Project.
The Ministry of Power has accorded approval on 12.07.2022 for incurring
expenditure on pre investment activities for an amount of 973 crore at
Nov.2021 Price Level.
Process for obtaining forest clearance has been initiated.
CEA vide letter dated 27.12.2022 vetted the cost estimates at completion level
for an amount of 22704.80 crore including ₹4593.41 crore for IDC and 1124.20
crore for enabling infrastructure.
MOU has been signed between NHPC Ltd. and JKSPDCL on 03.01.2021.
The project shall be executed by NHPC on BOOT basis for the period of 40
years.
MOEF&CC vide letter dated 10.06.2021 has conveyed the approval to the TOR.
EIA/ EMP studies is in progress.
Process for obtaining forest clearance is in progress.
DPR of Uri-I Stage-II HEP was submitted on 18.05.2022 and accepted by CEA for
examination in the meeting held on 20.06.2022.
15 out of total 23 clearances have been obtained from concerned
directorates of CEA /CWC/GSI/CSMRS etc.View entire presentation