Investor Presentaiton
Integrated Mine to Markets Scoping Study
Key findings - first 15 years of operations
《6
6 INTERNATIONAL
GRAPHITE
SPRINGDALE
Resource and Mine
父
Total Mineral Resource
49.3Mt @ 6.5% TGC
or
28.0 Mt @ 8.7% TGC
SPRINGDALE
Concentrator
500Ktpa concentrator
40-50Ktpa
concentrate
COLLIE
Micronising, Spheroidising
and Purification
8 Mo
20Ktpa UPSG
+
17Ktpa micronised
byproduct
COLLIE
Coating
18Ktpa CPSG
17Ktpa micronised
byproduct
7.5 Mt of ore mined
@ 9.5% TGC
-15% of resource
scheduled
Multi-decade
mine life
AISC lowest third
on global cost curve
@ US$485/t concentrate
CAPEX: A$76M
including 25% contingency
and pre-strip
CAPEX: A$124M
NPV: A$375M
IRR: 36%
AISC: US$1,603/t
Annual EBITDA:
A$78M
Battery Materials
CAPEX: A$217M
NPV: A$603M
IRR: 31%
AISC: US$2,699/t
Annual EBITDA:
A$142M
Battery Materials
*Refer ASX announcement dated 29 January 2024 for full supporting disclosures