Investor Presentaiton slide image

Investor Presentaiton

LOWER RISK & REDUCED TIMELINE TO PRODUCTION DECISION $18 million Program in 2021: Resource In-fill, Hydrology, Geotechnical and Metallurgical; • With $2 million Exploration drilling to potentially expand the mine life • • • . Initial permitting activities are expected to commence in parallel with the drilling; Peak Gold JV expects to complete Feasibility Study by the end of 2022 and Permitting in 2023; Wetlands Dredge and Fill (404) Permit from USACE; Other Permits Issued by State of Alaska Production expected to commence in 2024 DRILLING FEASIBILITY STUDY PERMITTING & FEASIBILITY CONSTRUCTION PRODUCTION Community Engagement • Tetlin Tribe has indicated their support for the project development plan; Continued Community Engagement Project construction expected to take approximately 1 year starting in 2023 Image used with permission from Kinross 28 CONTANGO ORE