The Application Process-Timeframes Maximum Access Timelines (Poles only) ■ Preconstruction Survey (and access denials): 45 days (+15 days for large jobs). Make-Ready Estimate: 14 days to provide/accept. Make-Ready Performance 60 days after payment (+30 days for wireless above communications space, +45 days for large jobs). ◉ Pole owner must notify existing attachers (upon payment of make-ready estimate) of planned make-ready. Large job: Lesser of 5% of pole owner's poles in a state or 3,000 poles (counted every 30 days) 21 Davis Wright Tremaine LLP