The marine ecosystem monitoring programme is being
implemented in the direct area of influence of the PERU
LNG port facility. Monitoring takes place every six months
(Autumn and Spring) to evaluate the effects of building
and operating the terminal on the marine environment.
The participatory nature of this monitoring means that
representatives (overseers) from associations of artisanal
fishermen in the direct area of influence of the PERU
LNG plant and the environmental authorities responsible
for our activities (OEFA, ANA, DICAPI, MEM, PRODUCE,
DIREPRO-ICA), were present while environmental quality
samples were taken of water, marine sediments and
marine biodiversity (plankton, benthic macroinvertebrates
and fish). The overseers accompany the monitoring effort
and are responsible for supervising and observing possible
social and environmental impacts relating to the port
operations. If the overseers find anything, they are recorded
and reported to their communities and to the company.
PERU LNG analyses the information collected during the
monitoring work and takes such corrective action as may
be required, thus continually improving the company's
operations.
Due to the state of emergency declared by the Peruvian State
to address the COVID-19 pandemic, fewer representatives
of the authorities took part in the monitoring effort in 2021.
AUDITS AND RELATIONSHIP WITH THE STATE
Audits of PERU LNG by the environmental authorities help to
maintain high operating standards and to confirm compliance
with legal requirements. In 2021 the Environmental
Evaluation and Monitoring Body (OEFA) carried out an audit
of the pipelines to verify an allegation that farm land in the
community of Vinchos, adjacent to WP 113+180 had been
adversely affected. The Supervising Body for Investment
in Energy And Mining (Osinergmin) also made a total of 57
visits, 30 to the plant and 27 to the pipelines. The auditors
made no observations.