CONSERVATIVE TIMELINE TO PRODUCTION (1) CriticalElements
Project Schedule, clear path to construction and commissioning
Assumption: Financing Completed by Sept. 2023
Value
Eng.
Study
Detail Engineering
12-14 months
2023 Sept.
YL
Tree clearing
site
preparation
Last long lead
Construction
Completion
equipment
delivered on site
Dec.
2025
Sept.
March
2024
April
Construction
± 20 months
Commissionning
and Ramp-up
6 months
(1) Completion of the activities on the timeline herein are estimates made by management based upon their current assumptions. This page contains "forward-
looking information" and readers are referred to the "Disclosure” statement in this Presentation. Risks include, but are not limited to, receipt of necessary
permits, successful results from earlier activities, the availability of the necessary financing, etc.