Lithium Corporation CONSERVATIVE TIMELINE TO PRODUCTION (1) CriticalElements Project Schedule, clear path to construction and commissioning Assumption: Financing Completed by Sept. 2023 Value Eng. Study Detail Engineering 12-14 months 2023 Sept. YL Tree clearing site preparation Last long lead Construction Completion equipment delivered on site Dec. 2025 Sept. March 2024 April Construction ± 20 months Commissionning and Ramp-up 6 months (1) Completion of the activities on the timeline herein are estimates made by management based upon their current assumptions. This page contains "forward- looking information" and readers are referred to the "Disclosure” statement in this Presentation. Risks include, but are not limited to, receipt of necessary permits, successful results from earlier activities, the availability of the necessary financing, etc. 2026 TSX-V:CRE 18