Renewable Energy B. Subsidiary/JV Mode (a) Under Construction Tentative Capacity S.No Name of Project (MW) Estimated Capital cost Expected Commissioning Tariff Schedule (Rs./unit) 1 Solar Power Project, Kalpi (UP) (Subsidiary-BSUL) 65 312.00 2022-23 2.68 Power (Partial Commissioning of 26 MW achieved on 09.07.2022) 2023-24 3.22 Power 2 Omkareshwar Floating Solar 88 589.16 Park (MP) (Subsidiary - NHDC) Total- (a) 153 901.16 22 एनएचपीसी NHPC Status of PPA Purchase Agreement has been executed between BSUL and UPPCL on 28.04.2022. Purchase Agreement has been Signed between MPPMCL, RUMSL & NHDC Ltd on 04.08.2022.