Upstream
+ narural gas
Azulão 2021 Highlights
24 million
m³ of natural gas produced.
< 59 >
Azulão-Jaguatirica
Integrated Project
Due to delays caused by the Covid-19 pandemic,
Jaguatirica II TPP started commercial operation
in February 2022, using as an input the natural
gas produced and liquefied in the Azulão field,
Amazonas, which has 2P reserves of 5.9 billion m³
(bcm) certified by Gaffney, Cline & Associates.
The TPP is installed in the municipality of Boa
Vista, in Roraima, and has an installed capacity
of 142 MW - enough to meet 70% of the state's
demand in an isolated system that has been
supplied by diesel and fuel oil generation systems
over the last few years. As the region lacks gas
pipelines and transmission line connected to
the SIN, Azulão gas is liquefied and transported
by road modal to Boa Vista, using the logistics
network itself employed for road transportation.
Thus, Jaguatirica II should displace a significant
part of the diesel oil generation that supplied
Roraima, allowing a reduction of approximately
35% in carbon emissions and 99% of NOx from
the isolated system of Boa Vista and adjacent
locations. Another differential is the fact that
Jaguatirica II TPP is the first in Brazil with Air
Cooled Condenser (acc) technology for cooling the
Azulão, Itapiranga, AM
water-steam cycle. In the process, hot air cooling
occurs with thermal exchanges with atmospheric
air through fans, without significant water
consumption.
The integrated project is an example of our
capacity to contribute to energy security,
industrial development and the minimization
of environmental impacts in regions not yet
connected to the SIN, from the energy transition
promoted with the use of natural gas to replace
more polluting fossil fuels. In this sense, after
leaving winners of the auction promoted by
ANEEL for commercialization of capacity reserve,
we will build Azulão TPP, gas powered, in the
municipality of Silves, Amazonas, replicating the
Model R2W. With an installed capacity of 295 MW
and investments of R$ 1.3 billion, the new plant is
expected to begin construction in the second half
of 2022, with delivery scheduled for the second
half of 2026.
MW average
self-generation of
for LNG production.
16,700 m³
18.7 MV
of LNG sent to Jaguatirica II TPP, in 424
cryogenic trucks.
Revenue of R$ 3.4 million with the
commercialization of 1,000 m³ of condensate.
Plant operating with
74
employees (43%
of labor in the regions of Silves and Itapiranga).
25 people
from the region have completed Operator
Training courses that we offer.