Investor Presentaiton
THE ROSE PROJECT: MINE & CONCENTRATOR
OPEX details (1)
Operating costs per tonne processed
Mining ($4.56 per tonne)
Processing
G&A
Transportation (FOB Port)
CriticalElements
Lithium Corporation
C$96.73
$37.89
$19.88
$20.30
$18.66
C$/t Li,O
Concentrate
US$/t Li₂O
Concentrate
Operating costs per tonne of concentrate
Mining
701
540
274
211
Processing
144
111
General & Administration
147
113
Transportation
135
104
Total Operating Costs
701
540
SG&A
35
27
Royalties
30
23
Total Operating Costs (w. SG&A & Royalties)
Less Tantalite Credit
766
590
52
Total Operating Costs (after tantalite credit)
714
40
550
Source: Critical Elements Lithium Corporation - NI 43-101 Technical Report on Rose Lithium-Tantalum project feasibility study dated July 26, 2022
(1) Dollar figures in Canadian dollars unless otherwise stated; feasibility study assumes exchange rate of US$0.77/C$