Investor Presentaiton

New Paint Factory Dulux MERRIFIELD Status update - - All planning and building approvals received Site works commenced in December 2015 Pricing firm on 50% of capital - Building construction commenced March 2016 VAUGHAN Dulux On time and budget Commissioning (mid 2017) Production (late 2017) Benefits of new factory - Emerging paint technologies - Lower costs - At least NPV neutral - Reduced fire and flood risk vs. Rocklea DuluxGroup Imagine a better place 19